Location: Three Bridges, Sussex

 

Value: Circa £250k

 

 

ALS completed the installation of a number of HV Cable containment routes, installation of concrete bases and steel structures at a UKPN substation site in Sussex.

 

ALS mobilised a number of of specialist Power Utilities teams to complete this project. 

 

This project produced many challenges that ALS, with our wealth of experience are able to overcome including:

 

-Mobilising works inside a working substation

-Programme outage and interface restrictions

-Swift mobility of teams

 

 